One of London's longest-running roadwork projects is finally complete: 'The nightmare is over'

One of London's longest-running roadwork projects is finally complete: 'The nightmare is over'

Gallows Corner has finally reopened to motorists 15 months after work began
'London potholes are so deep you can use them to play golf!'
WEST END FINAL

Reform-led Havering Council said the “nightmare is finally over” as Gallows Corner finally reopened to motorists after more than a year.

A “major renewal” of the busy flyover and roundabout that links London to Essex has been completed 15 months after it began, bringing to an end one of London’s longest-running roadwork sagas.

It had initially been slated to reopen in spring, but delays in replacing water mains saw the project pushed back for months.

Council leader Councillor Keith Prince said: “The nightmare is finally over for residents and businesses who have had to put up with months of unacceptable disruption at Gallows Corner.

“When I became leader [in May], I set a clear end date of October and have been pushing hard to make sure Transport for London and Essex & Suffolk Water complete these works and honour that commitment.

“I am pleased to see that they have finally fully reopened the junction and flyover this morning.

“We hope this finally marks the end of the disruption caused to local people, but we also know the pain suffered by businesses will be felt for a long time.”

<p>Havering council leader Keith Prince</p>
Havering council leader Keith Prince

Stuart Harvey, TfL’s chief capital officer, said: “We’re pleased to confirm that Gallows Corner Flyover has fully reopened following the completion of this major programme of works.

“We’d like to apologise to local residents, businesses and road users for the delays to these works and thank them for their patience while this essential project has been carried out.

“The flyover was originally built as a temporary structure and this work has secured its future for years to come, allowing us to remove restrictions and improve journeys for everyone who relies on this important route.”

<p>ROMFORD, ENGLAND - MAY 02: Roadwork continue at Gallows corner on May 02, 2026 in Romford, England. The Chief executive of Havering Council, Andrew Blake-Herbert has called the works an "unacceptable mess", after further delays were recently announced. In the upcoming May 2026 local elections, the London Borough of Havering has emerged as a primary target for Reform UK, with polling suggesting the party could secure over 35% of the vote and potentially take control of the 55-seat council. (Photo by Dan Kitwood/Getty Images)</p>
The roadworks at Gallows corner

Gallows Corner was opened in the 1970s and was nearing the end of its lifespan when TfL began the works last year.

Though Havering motorists can once again travel around the east, the council is set to continue its push for compensation.

“We wrote as recently as last week to [Mayor of London] Sadiq Khan and [Deputy Mayor of London for Transport] Seb Dance about compensation.